PLTU KALSEL 1 COAL FIRED POWER PLANT 2x100MW

Foundation

PLTU KALSEL 1 COAL FIRED POWER PLANT 2x100MW

Slipform

PLTU KALSEL 1 COAL FIRED POWER PLANT 2x100MW

Lifting Platform

PLTU KALSEL 1 COAL FIRED POWER PLANT 2x100MW

Liner Fabrication

The Company has been awarded in 2016 by Hyundai Engineering Co. Ltd-HEIN Global Utama to build a 125m height reinforced concrete chimney with 2 steel liners ID.3640mm for the PLTU Kalsel 1 Coal Fired Power Plant 2x100MW in Indonesia.
All activities including engineering, procurement, and construction will be performed by Chimneys and Refractories International Srl.
Piling and foundation activities started in beginning of 2017 and the whole chimney construction is expected to be completed in middle of 2018.

The scope of work included:

  • Structural and detail engineering design
  • R.C. Windshield slipforming
  • Steel platform assembling and lifting
  • Steel liners assembling and lifting including mineral wool mattress
  • Electrical and lightning system installation
  • Ancilarry items installation