MONG DUONG 1 THERMAL POWER PLANT

Foundation

MONG DUONG 1 THERMAL POWER PLANT

Slipform

MONG DUONG 1 THERMAL POWER PLANT

Liner Fabrication

MONG DUONG 1 THERMAL POWER PLANT

Platform lifting

MONG DUONG 1 THERMAL POWER PLANT

Inside Chimney

MONG DUONG 1 THERMAL POWER PLANT

Windshield Painting

The Company has been choosen by Hyundai Engineering and Construction to build No.2 220m height reinforced concrete multiflue chimney with 2 steel liners ID.4400mm for the MONG DUONG 1 THERMAL POWER PLANT 2x500MW in Vietnam.
All activities including engineering, procurement, and construction will be performed by Chimneys and Refractories International Srl.
Piling and foundation activities started in November 2012.

The scope of work included:

  • Structural and detail engineering design
  • R.C. Windshield slipforming
  • Steel platform assembling and lifting
  • Steel liners assembling and lifting
  • Electrical and lightning system installation
  • Ancilarry items installation